Wednesday, March 15, 2017

Making Smart Factories A Reality For Manufacturers

Making Smart Factories A Reality For Manufacturers: Smart factories are the future of manufacturing but what is preventing them from being a reality on shopfloors today?

Re-blogged by GMT

How Boeing Transports Their 100-Foot Wings Through Washington

How Boeing Transports Their 100-Foot Wings Through Washington: Transporting one of Boeing’s massive 100-foot wings 70 miles through the state of Washington takes three different vehicles.

Re-blogged by GMT

Video: The Latest Engineering Innovations From January 2017

Video: The Latest Engineering Innovations From January 2017: From biomedical sleeves to prevent heart failure to hoverboards, IEN reports on the latest product developments.

Re-blogged by GMT

Friday, January 6, 2017

GMT LATHE CHUCK MOUNTING



MOUNTING THE CHUCK
1. Check the location dia. and face of the machine spindle for Radial and Axial Runout using a Dial gauge. Maximum permissible Radial Runout and Axial Runout of the spindle shall not exceed by 0.005 mm.
2. Mount the chuck flange on the machine using the necessary clamping screws or the special provisions made by the manufacturers.
3. Check the flange for true running for Radial and Axial Runout and ensure that these do not exceed 0.005 mm.
4. Connect the drawtube/draw bar to the cylinder. If the drawtube/draw bar is to be fitted into the cylinder piston rod, ensure that the piston rod is retracted. If fitted at the intermediate position, the anti-rotation stop pin of the piston may be damaged.
5. Mount the Cylinder Flange on to the spindle rear side and check the flange for true running for Radial and Axial Runout and ensure that these do not exceed 0.005mm.
6. Mount the cylinder on to the cylinder flange.
7. Connect the pressure ports of the cylinder by hose.
8. Actuate the cylinder at low pressure (4-5kgf / cm2) two or three times and set the piston towards the cover end and switch off the hydraulic power.
9. Remove the cover from the chuck by removing cover clamping screws.
10. Keep the Wedge in fully de-clamped condition (At this position, the jaws will be fully opened).
11. Clean the chuck location diameter and hold the chuck in such a way that the collar just touches the drawtube end. Tighten the collar on to the drawtube using the special spanner provided, until the chuck sits properly on the flange face. Align the chuck clamping holes with the tapped holes provided on the chuck flange.
12. Tighten the collar with drawtube(in case of draw bar, tighten the wedge screw into the drawbar) and chuck clamping screws simultaneously till the chuck location face butts against the flange butting face.
13. True up the periphery of the chuck with the help of plastic mallet.
14. Ensure there is a gap (approximately 0.5 mm) between the wedge face and body inner face by adjusting wedge screw or wedge collar.
15. Reassemble the cover.
NOTE:
1. Before tightening the chuck flange (Adaptor plate for mounting the chuck) with the Taper nose of the machine spindle, ensure that the clearance between the spindle face and chuck flange butting face is not more than 0.03mm.
2. The flatness of the face of the chuck flange after machining on the machine can have only concavity maximum 0.01mm. Convexity is not permitted. Check with the help of straight edge for blue bearing.
3. Actuate the actuator and check the jaws are moving freely and check for the jaw stroke.

GMT CHUCK DISMANTLING PROCEDURE



1.       Remove the hard jaws / soft jaws from the base jaws by loosening the socket head screws along with the T’ Nuts.
2.       Remove the cover  with cover adaptor (if available) from the chuck.
3.       Loosen the chuck clamping screws which are used for mounting the chuck on the flange.
4.       Do not loosen the screw  fully threads must be engaged with flange .
5.       Ensure that a wooden plank is placed below the chuck on the guide ways of the lathe.
6.       Using the special spanner (Provided along with chuck), rotate the collar  till the drawtube is completely disengaged.
7.       If it is special execution chuck, then using the Allen key (provided with the chuck) loosen the wedge screw till it disengages from the draw bar.
8.       Then loosen the chuck clamping screws fully from the flange, so that the chuck comes out from the flange.
NOTE : DO NOT LOOSEN THE COLLAR OR WEDGE SCREW WITHOUT LOOSENING THE CHUCK CLAMPING SCREWS.
9.       After removing the chuck from the machine spindle, keep it in a table and pull out the wedge along with wedge adaptor and collar.
10.   Push the base jaw towards the wedge bore of the chuck and remove them.

NOTE : DO NOT HAMMER THE BASE JAWS WITH STEEL. ALWAYS USE ALUMINIUM OR PLASTIC MALLET.